Typical Construction Process

10hr_06_program-schedule

Authority Submission Procedure

Development Control Submission (Typically 2-3 Months)

  • CBPU/PUB
  • LTA (Roads)
  • LTA (Carpark)
  • Nparks
  • FSSD

Building Plan Submission (Typically 2-3 Months)

  • CBPU/PUB
  • LTA
  • NParks
  • FSSD
  • Structural Design

Construction Process (Typically 19 Months)

Building Works

  • Excavation & Temporary Works
  • Superstructure
  • Substructure
  • Brickworks/Partitions
  • Door Installation
  • Aluminium Works

Finishing Works

  • Plastering
  • Wall Finishing
  • Ceiling
  • Painting
  • Floor Finishing
  • Metal
  • Glazing
  • Carpentry/Joinery

M&E Service Works

  • Sanitary and Plumbing
  • Electrical and Security Systems
  • Lift
  • ACMV

External Works

Landscaping & Turfing Works